We thought it would be useful to take a look back at a major project one year later and get the client's perspective. For this article we hired free-lance writer extraordinaire Sara Cardine to go back and talk with the folks at Westridge about how going solar has worked out for them. Here is part one of Sara's report (with links to parts two and three at the end.)
For the past 100 years, Pasadena's Westridge School for Girls has prided itself on providing a top-notch education that grooms young women into the leaders of tomorrow.
As part of a legacy of bringing cutting-edge ideas and innovation to campus and making it all come alive in the classrooms, school officials have made it a goal to pursue and complete at least one project related to sustainability on campus each year.
In late 2011, looking forward to the next year, they decided to address a perennial request made by parents and students over the years: that an air-conditioning system be installed in the school gymnasium to keep crowds cool on hot days. While the school could likely raise funds from the parent community to purchase and install a system, the financial and environmental impact of running it and creating a new drain on the power supply were less than sustainable, says Brian Williams, Westridge's Director of Facilities.
So, to offset the cost and energy consumption of the desired air-conditioning unit, officials decided to fundraise for another project at the same time, one that would mitigate the cost and consumption of the A/C.
They asked parents and students if they'd be willing to raise money to install a solar system on school grounds.
Big Plan on Campus
Solar energy was not exactly new to the school. In 2009, Westridge had installed a small system on its newly built LEED-Certified Platinum science and math building. There some of the panels were placed near the ground, where students could see them up close and interact with the technology.
For the new project, however, school officials were thinking much bigger. They wanted to maximize energy savings by installing a large-scale system that would provide a solid and swift return on their investment and take advantage of a local rebate being offered by Pasadena Water and Power (PWP) that was set to decrease drastically after the end of the year.
Ideally, the new installation would generate enough energy to cover the usage from the A/C in the gym and still supply additional power to other buildings on the campus, saving on the school's overall monthly electric bill.
At the outset, there were no specific parameters for the project, Williams said, just a location.
"We found our biggest roof and said, 'Fill it up,'" he says.
The south-facing slope of the roof of the Fran Norris Scoble Performing Arts Center would be the perfect place to set up a large installation.
|
A Picture-Perfect Roof for Solar
|
With an area of approximately 4,000 square feet, it received direct sunlight throughout most of the day and was elevated enough to tidily keep the operation out of sight.
Doing their Bidding
Williams turned to three different solar companies, seeking estimates to help define the scope of the project and determine a total cost that would guide the school's fundraising efforts.
The first two companies Williams considered were those the school had worked with on past projects. One was a large, international solar provider that had worked on the 2009 science building installation. The other had previously worked with Westridge on nearby residential properties.
Run on Sun, the third provider approached regarding the installation, was the only one the school had not personally worked with before. The Pasadena-based company had contacted school officials earlier that year and delivered a presentation on its installation process, qualifications and services provided. That presentation was fairly comprehensive, and made enough of an impact for Westridge to include Run on Sun in the bidding process.
"We didn't have any actual experience with them, but they had very good references that we checked as we went through the bidding process," Williams explains.
Finding the right contractor for the job was a thorough search that employed analysis and research. But beyond that, Williams, who's worked in the facilities department for more than two decades, relied on his own gut instinct and experience to determine which company could best get the project done in a short amount of time and leave no detail unchecked.
Since Westridge is a privately funded nonprofit, it is not under the same obligation as public entities to accept the lowest contractor bid. Cost, however, was still a primary consideration in selecting an installer.
"I have a fiduciary responsibility in my job to make sure the projects we do here are cost-effective and help maintain our campus in a positive way," Williams says. "I can't do anything that doesn't make fiscal sense."
The cost estimates provided by the three companies for an approximately 50 kW system were not that disparate from one another, coming in at about $4.25 per watt. One thing Westridge did have to be cautious about in its review of the estimates, however, was the possibility of a provider initially underbidding the project with the intention of requesting additional funds through change orders after a contract had been signed. The contractor who was truly right for the job would be one who provided an accurate estimate up front and diligently held true to that figure.
When considering the PWP rebate, Williams knew the school stood to save about half the total cost of the installation over the course of five years. Additionally, all three bidders told Westridge officials they could expect to see a full return on their investment in about seven years. Overall, the project made great financial sense.
Since the cost estimates that came in from the three bidders were relatively similar, Williams also analyzed each company's references, experience and credentials. For example, he did consider installers certified by the North American Board of Certified Energy Practitioners (NABCEP) to have an advantage over uncertified companies. Another important factor was the presence of a licensed electrician on the staff. "It's an electrical installation, and I wouldn't let anybody who wasn't a licensed electrician be on site," he says. "I'm guessing the city wouldn't allow it either."
Throughout the selection process, Westridge officials knew they were working under a bit of a time crunch. If they missed the window to apply for the PWP rebate, the project would end up costing significantly more than the amount they had raised. Because of this, hiring an installer who could successfully submit all the paperwork before the fast-approaching deadline, and one they could trust to get the application process 100 percent right the first time, was of critical importance.
In this regard, Run on Sun was a standout, Williams says. They promised to take care of all the paperwork, filing within the deadline period and eliminating the extra bureaucratic steps the school would otherwise have had to take.
"They managed the whole process - I basically just had to sign the form," he says.
The fact that Run on Sun had a strong working relationship with the city of Pasadena was another important consideration that worked in its favor, given Westridge's own solid standing in the community. The attention to detail and professional accountability demonstrated by the company throughout the bidding process brought the local provider to the top of the list, making the ultimate decision to go with Run on Sun an easy one, Williams says.
"It was a combination of the cost, return on investment, their relationship with the city, the impression we had with the provider, how they presented the information and their references. We looked at all of it."
This Case Study continues with Part Two: Run on Sun Gets it Done! and concludes with Part Three: Advice to the Solar Reluctant.
The preceding is an excerpt from Jim Jenal's upcoming book, Commercial Solar: Step-by-Step, due out this summer. |