Tag: "lg solar panels"

05/04/12

  08:15:00 am, by Jim Jenal - Founder & CEO   , 1186 words  
Categories: Commercial Solar, Non-profit solar, Westridge PAC Project

On the Roof - Installing Solar at Westridge - Part 4

Our first three installments saw us secure our rebate reservation, successfully pull our permits, and deal with a host of challenges on the ground.  But now the real fun starts - in this episode we will document the heart and soul of this project, “Up on the Roof!”

Projection

Solar projects actually begin on a computer screen as the designer tries to map what is known about the roof, the utility service, and the client’s needs into a coherent proposal.  As the project progresses through the rebate and permitting processes, that design is refined - and as we have seen, sometimes altered.  But the trick of any implementation is to go from the designer’s plan to an actual system on the roof - starting with getting the attachments in place.

Jim and Brad confer over the plansNearly ancient methods, tape measures and chalk lines, are the essential tools in this process.  Since a solar array is essentially a grid, the trick is to project what is on the plans into a corresponding grid on the roof.  Precision and accuracy are the key to making this work, but roofs are notoriously inconsistent places!  What seemed to be square, isn’t always.  What appeared to be flat, actually has its own peaks and valleys.  While our projection onto the roof proved easy enough, we were about to discover that what you see - or were told - isn’t always what you get!

There’s What You Plan and What You Get

Our biggest design challenge had been the need to account for the somewhat unusual roof construction that we had to accommodate.  In particular, our underlying roof structure was a  20 gauge, type B steel deck, overlayed with multiple layers of plywood, foam insulation and roofing materials.  Given the thickness of those layers we had determined that we would need to use four,  8-inch-long, self-tapping screws to secure our “FastFoot” anchors to the roof.  We had purchased hundreds of those screws - along with a top-of-the-line Hilti cordless driver - to do the job.  But something wasn’t right.

As we started making our first few attachments it was clear that not all of them were reaching the steel deck!  Apparently in some places the actual thickness from the roof to the deck exceeded the 8″ reach of the screws.  Visual inspection from a scissors lift inside the building confirmed what we suspected - clearly not all of the screws were penetrating the deck, yet in other places, all four screws penetrated without difficulty.  There was only one solution to the problem of our inconsistent roof - longer screws!

Fortunately, we were able to order some 9″ screws from the manufacturer - the longest that they made.  They did the trick - now we could be certain that every FastFoot plate was properly secured.

Lean on Me

The changes to our plans imposed during the permitting process meant that we were very tight on space.  At the top of our array we had to install 3 sub-panels, each of which had to handle three branch circuits that made up that sub-array.  Our original plan was to build a triangular cross brace out of unistrut to support the sub-panels.Sub-panel with braces Unfortunately, given our close quarters, the solar panels needed to come right up to the supports for the sub-panels - a cross-brace system would take up too much space.

Instead, we designed a set of steel braces that were bent at precisely the angle that we needed - 103° - to allow our sub-panels to be perfectly vertical on our 13° sloped roof.  The design was easy, but could we get them fabricated fast enough to keep the project on track?  We knew of a small metal shop near our offices and we took the design to them - yes, they said, they could produce the six parts that we needed for $100 and they would have them in the morning - would that be soon enough?!!!

This turned out to be a very elegant solution to our problem.  Using two FastFoot anchors, we attached unistrut to them and then bolted our braces to that.  When combined with the rigid conduit feeding the sub-panel, we ended up with a very solid solution. 
Next problem!

Need a Lift?

The roof of our building was reachable by a series of three ladders traversing three different roof levels.   Josh delivers Enphase micro-inverters to the roof via boom liftWhile this was acceptable for getting personnel to and from the roof, it would never work for transporting hundreds of feet of rails, to say nothing of 209 solar panels!

Enter the boom lift - the same one that was unceremoniously dropped off for us by parking it under a No Parking sign!

Whether transporting rails, solar panels, or the Enphase micro-inverters as you see in this picture, the boom lift provided us with an efficient means of moving large amounts of gear up to our work site on the roof.  Operating a device that articulates in multiple dimensions in relatively tight quarters takes skill and great attention to detail.  (It also makes for some pretty cool looking photos!)

Connect the Dots

Once the rails were installed, the Enphase micro-inverters could be mounted and the process of running a continuous ground wire and the creation of the Enphase map could begin.

Ready for panels

Since this was an Enphase system, we would be able to monitor the performance of the array down to the individual solar panel/micro-inverter pair.  (Indeed, this monitoring ability was a key selling point for the system to the school as it nicely meshed with the school’s educational mission - more on that in our upcoming video!)  Each micro-inverter has a serial number that was carefully peeled off and affixed to a “map” that showed where each inverter was located on the roof.  As part of the commissioning process, we transferred the map data onto the Enphase website and built a true representation of how the system was laid out on the roof.

Now all we needed was to install the solar panels themselves!

Ralph and Josh installing panels

Careful attention to detail during this last step is rewarded with an array that aligns precisely and fits as planned.  Using the Enphase Envoy and a laptop computer, we could verify that each and every panel was properly connected and functioning as expected.  We could be confident that there would be no surprises that would need to be resolved later!

That gave us one last task for the boom lift - finished photographs.  Here’s our favorite:

Westridge PAC roof - solar project installed

Three inspections later - fire, building & safety, and PWP - and we were ready to officially go live.  Here’s how the system appeared on the Enphase Enlighten website one recent sunny day:

Westridge PAC solar system performance

The students at Westridge will be able to analyze the performance of this system for years to come, providing a first hand experience of how renewable energy works and can make a difference in our lives - what a great lesson to learn!

Chapter the Last

Which brings us to the end of this series - almost.  In our final installment you will see the video that we have produced for this project and you will hear from the Head of Westridge School, Elizabeth McGregor, Facilities Director Brian Williams, and three wonderful students talk about how this project plays into the larger mission of the school.  You won’t want to miss it!

 Permalink
  08:15:00 am, by Jim Jenal - Founder & CEO   , 1096 words  
Categories: Commercial Solar, Non-profit solar, Westridge PAC Project

On the Ground - Installing Solar at Westridge - Part 3

In parts 1 and 2 of this series, we documented what went into securing the rebate reservation and the process by which we secured our permits.  Now the actual work could begin - and that work starts on the ground.  So in this Part 3, we will look at the staging that was required for this production and take a close-up look at some of the heavy lifting that was needed far below the array itself.

A project the size of what we were going to install at Westridge - 52.3kW - involves thousands of parts, all of which not only must go together properly for the system to work and be safe, but they must arrive in a timely fashion!  For example, here’s just a sample of the parts that were needed for this job: hundreds of FastFoot plates, thousands of screws, hundreds of flashings, standoffs, and flange connectors, dozens of rail sections, mid-clamps, end-clamps, ground lugs and splices, to say nothing of 209 micro-inverters and solar panels!  Collectively these products came from five different distributors in four different states.

Needless to say, not everything goes as smoothly as you might like when you are pulling together all of these pieces.  UPS likes to brag about Logistics, but we found some of their logistics to be highly illogical.  Such as their sending two shipments that were sitting in an LA warehouse on a frolic and detour down to San Diego for the weekend, instead of driving them the twelve miles up the road to our job site!

boom liftEqually baffling were the folks who delivered our boom lift to the job site late on a Friday evening without even a phone call and just parked it out on the street - in front of a No Parking sign!

Seriously…

Would you leave this…

 

No parking!

Here?  Right - neither would we!  (And yes, the keys were in it!) The unscripted appearance of our boom lift prompted a puzzled call from the facilies director at Westridge:

Brian: “Were you folks expecting a boom lift to be delivered?”

RoS: “Yes, they are delivering it tomorrow morning.”

Brian: “Well, it’s here - and they left it on the street next to a No Parking sign.”

RoS: (Eek!) - “Really?  We’ll be right there!”

Like I said, not everything can go exactly as planned, but soon enough, everything arrived and in good condition.

Our staging area was set with:

LG solar panels in staging area

LG Solar Panels

Enphase micro-inverters in staging area

Enphase Micro-inverters

Unirac rails in staging area

Unirac Solarmount (Evolution) racking parts

Lots of wire!

And lots of wire!

Transformation

Our first main task on the ground, now that everything was at hand, was to install our transformer.  This project required a transformer to step-down the voltage from the utility service (480 volts, three-phase) to the voltage that would be used by our micro-inverters (208 volts, three-phase).

Setting the Stage

Westridge transformerOur transformer was a 700 lb beast that had to be installed on a concrete pad (that we had to pour) in the equipment storage area on the East side of the building.  To secure the transformer to the pad, we would imbed bolts into the pad and then maneurver the transformer on top of the bolts and anchor it with washers and nuts.  Two key challenges there - first was to guarantee that our bolts were precisely positioned in the pad since the transformer gave us very little margin for error.  Second was to get the transformer in place on top of the bolts without damaging them.

pad prepWe solved the first problem by drilling into the existing concrete and securing our bolts into the ground with heavy duty anchors - as you see here with the framework for the pad surrounding them.

Then, when we were ready to fill in the form with concrete, we added some framing at the top to try and keep the bolts as plumb as possible, as you see here:

concrete being added for pad

The Big (Not So) Easy

That took care of problem number one, but what to do about problem number two? Now that the pad was dry, the challenge became getting our transformer into place.

ready for the transformer

Our solution would make any student of ancient cultures proud - we crafted a wooden platform over the pad and slid the transformer from its pallet onto the platform.  Then we lifted each edge, one at a time, and placed blocks of wood under each corner.  That allowed us to remove the platform and then begin lowering the transformer over the bolts by carefully removing a block at each corner.

Very little margin for errorAs we removed each block, the transformer came closer to the bolts protruding from the pad.  We could push the transformer - gently - so that it aligned with the bolts.  Ultimately, the last block was removed and the result was a complete success with just the right amount of angst along the way!

But as you can see, we really didn’t have much margin for error!

The Art of Conduit

In addition to our transformer, there were several other pieces of gear that had to be mounted on the ground including a 200 Amp sub-panel, two disconnect switches and a performance meter.  Linking them all together is the conduit through which our conductors would be pulled.

The art of running conduitPasadena requires rigid metal conduit (instead of EMT) to be used for solar power systems wherever it is accessible on the outside of a building.  That offers some additional safety, but it comes at a cost - especially given that we were using 1.25″ conduit for most of our runs.  Rigid conduit of that dimension is heavy and cannot be bent by hand.  Instead, a motorized pipe bender was the order of the day - and it took some really skilled craftsman named Don and Josh to get our conduit in place and looking good.

It really is an art, as much as a science, and when done with care and precision, the result is quite appealing!

Pulling it Together

Our final ground-based task was to pull the conductors through the conduits.  Our longest pull was 245′ - not quite a football field, but close!  Moreover, that longest pull had multiple bends as we routed the conduit to make it as invisible from the ground as possible.  (To complete the task of making the conduit “disappear” to the greatest extent possible, the client painted the conduit to match the walls and the trim!)

At the end of a very long, drizzly Saturday, we were rewarded with having our conductors fully in place from the utility disconnect switch and performance meter socket:

utility disconnect and performance meter socket

… to our disconnect switch adjacent to the transformer:

transformer disconnect

Our penultimate installment will take you to the roof where the real action takes place.  So buckle in, the next chapter isn’t for the faint of heart!

Search

Jim Jenal is the Founder & CEO of Run on Sun, Pasadena's premier installer and integrator of top-of-the-line solar power installations.
Run on Sun also offers solar consulting services, working with consumers, utilities, and municipalities to help them make solar power affordable and reliable.

Ready to Save?

Let’s Get Started!

We're Social!



Follow Run on Sun on Twitter Like Run on Sun on Facebook
Run on Sun helps fight Climate Change
Community CMS